Evaluating on Application of Lean Construction of Toll Road Projects in Indonesia
DOI:
https://doi.org/10.29103/tj.v16i1.1285Keywords:
construction, cost, lean construction, time management, waste materialAbstract
Abstract
Lean construction boosts productivity, reduces costs, and enhances overall project performance. This research looks at how PT Nindya Karya implements lean construction in a toll road project. The study site is the Bayung Lencir-Tampino Toll Road project. The approach taken is quantitative, including statistical analysis and a final report document. The study found that implementing lean construction concepts in this project had a beneficial impact. The project was completed faster than projected, taking 415 days instead of 574 days, resulting in a time savings of roughly 27.7%. The Just-in-Time approach and the Last Planner System both helped to reduce time waste and material delays. The project team used a target value design, which ensures that resources are used in accordance with specified criteria and there is no excess or deficit of materials. Lean construction has resulted in significant cost savings for the project, with expenses lower than expected, resulting in an 8.67% surplus on the contract value. As a suggestion, future research could look into the impact of lean construction on projects other than toll highways.
Keywords: construction; cost; lean construction, time management; waste material
Abstrak
Konstruksi ramping meningkatkan produktivitas, menurunkan biaya, dan meningkatkan kinerja proyek secara keseluruhan. Studi ini meneliti bagaimana PT Nindya Karya menggunakan konstruksi ramping pada proyek konstruksi jalan tol. Lokasi studi ialah proyek Jalan Tol Bayung Lencir-Tampino. Metode yang digunakan adalah kuantitatif, dengan analisis statistik, dokumen laporan akhir, dan kuesioner. Hasil penelitian mengungkapkan bahwa penerapan prinsip konstruksi lean dalam proyek ini berdampak positif. Proyek ini selesai lebih cepat dari yang diharapkan, dengan total durasi 415 hari dibandingkan dengan jangka waktu awal 574 hari, sehingga menghemat waktu sekitar 27.7%. Metode Just-in-Time dan Last Planner System membantu menghilangkan pemborosan waktu dan keterlambatan material. Tim proyek mengadopsi desain nilai target, yang memastikan bahwa material digunakan berdasarkan kebutuhan yang ditentukan dan tidak ada kelebihan maupun kekurangan material. Konstruksi ramping telah menghasilkan penghematan biaya yang signifikan untuk proyek dengan biaya yang lebih rendah dari yang diantisipasi, sehingga menghasilkan surplus sekitar 8.67% dari nilai kontrak. Sebagai saran untuk penelitian selanjutnya disarankan untuk meneliti pengaruh Konstruksi ramping pada berbagai proyek selain jalan tol dan sebagainya.
Kata kunci: konstruksi; biaya; konstruksi ramping, manajemen waktu; bahan limbah
References
Adhitama, L., & Saraswati, D. M. (2023). Evaluasi Lingkungan Kerja berdasarkan Aspek 5R pada Usaha Konveksi Sherly Bordir Departemen Produksi dan Penyimpanan. Jurnal Tekstil: Jurnal Keilmuan Dan Aplikasi Bidang Tekstil Dan Manajemen Industri. 6 (2), 50–59. https://doi.org/10.59432/jute.v6i2.72
Aisyah, R. A., Gunawan, K., & Gazali, A. (2023). Lean Construction Through Waste Register Method: A Case Studies Project in Indonesia. Proceedings of the 31st Annual Conference of the International Group for Lean Construction (IGLC31), 1303–1313. https://doi.org/10.24928/2023/0204
Amalia, N., Ulfa Nabila, , Abbas, F. M., & Putra, W. D. (2024). Penerapan Prinsip Lean Contruction Dalam Sistem Manajemen Mutu Konstruksi Untuk Meningkatkan Produktivitas Dan Kualitas. Journal of Comprehensive Science. 3 (5), 91-101.
Anastasiu, L., Câmpian, C., & Roman, N. (2023). Boosting Construction Project Timeline: The Case of Critical Chain Project Management (CCPM). Buildings, 13(5), 1–35. https://doi.org/10.3390/buildings13051249
Ansell, M., Evans, R., Holmes, M., Price, A., & Pasquire, C. (2009). Collaborative working in highways major maintenance projects. Proceedings of Institution of Civil Engineers: Management, Procurement and Law, 162(2), 59–67. https://doi.org/10.1680/mpal.2009.162.2.59
Aravindh, M. D., Nakkeeran, G., Krishnaraj, L., & Arivusudar, N. (2022). Evaluation and optimization of lean waste in construction industry. Asian Journal of Civil Engineering, 23(5), 741–752. https://doi.org/10.1007/s42107-022-00453-9
Arunizal, S., Wardhani, D. H., & Windarta, J. (2024). Penerapan Value Stream Mapping (VSM) untuk Menurunkan Lead Time Process dan Meningkatkan Kinerja Aktivitas Pengadaan di Site Tambang. Jurnal Profesi Insinyur Indonesia, 2(3), 141–150. https://doi.org/10.14710/jpii.2024.23282
Aziz, A. F. A., & Irfan, N. M. (2020). Evaluasi Implementasi Last Planner System pada Proyek-Proyek Pembangunan di PT. Waskita Karya (Persero) Tbk. Universitas Diponegoro.
Bajjou, M. S., & Chafi, A. (2021). Lean construction and simulation for performance improvement: a case study of reinforcement process. International Journal of Productivity and Performance Management, 70 (2), 459–487. https://doi.org/10.1108/IJPPM-06-2019-0309
Bhargav, D., Koskela, L. J., Kemmer, S., & Koskenvesa, A. (2015). Suggestions to improve lean. 23rd Annual Conference of the International Group for Lean Construction, July, 193–202. http://iglc.net/Papers/ Details/1225/pdf%0Ahttp://iglc.net/Papers/Details/1225
Bigwanto, A., Widayati, N., Wibowo, M. A., & Sari, E. M. (2024a). Key Performance Indicators (KPI) to Measure Effectiveness of Lean Construction in Indonesian Project. Sustainability (Switzerland), 16 (15), 1–14. https://doi.org/10.3390/su16156461
Bigwanto, A., Widayati, N., Wibowo, M. A., & Sari, E. M. (2024b). Lean Construction: A Sustainability Operation for Government Projects. Sustainability (Switzerland) , 16(8), 1–16. https://doi.org/10.3390/su16083386
Dara, H. M., Raut, A., Adamu, M., Ibrahim, Y. E., & Ingle, P. V. (2024). Reducing non-value added (NVA) activities through lean tools for the precast industry. Heliyon, 10(7), e29148. https://doi.org/10.1016/j.heliyon.2024.e29148
Dowson, J., Unterhitzenberger, C., & Bryde, D. J. (2024). Facilitating and improving learning in projects: Evidence from a lean approach. International Journal of Project Management. 42(1), 102559. https://doi.org/10.1016/j.ijproman.2024.102559
Dytczak, M., Ginda, G., Jastrząbek, B., & Wojtkiewicz, T. (2013). A Feedback-Aware Valuation of Construction Project Execution Time. https://doi.org/10.13033/isahp.y2013.003
Elmalky, A., Dokhan, S., & El-Dash, K. (2024). Impact of Adopting Lean Principles on Construction Waste in Developing Countries. Engineering Research Journal (Erj), 53, 28–93. https://erjsh.journals.ekb.eg
Gaio, J., & Cachadinha, N. (2011). Suitability and benefits of implementing lean production on road works. 19th Annual Conference of the International Group for Lean Construction 2011, IGLC 2011, 168–177.
Hermina, S., Untu, S., Dundu, A. K. T., & Mandagi, R. J. M. (2014). Application of lean project management method in construction project planning (Case study: Construction of Mantos building phase III). Journal of Civil Statics, 2(6), 321–322. https://ejournal.unsrat.ac.id/index.php/jss/article/view/5827
Li, M., Ma, Z., & Tang, X. (2021). Owner-dominated building information modeling and lean construction in a megaproject. Frontiers of Engineering Management, 8(1), 60–71. https://doi.org/10.1007/s42524-019-0042-3
Lorenza, U., Soedira, R. A., Ramadiani, M. A., & Rizal, F. Z. (2024). Implementation of the Just in Time (JIT) method in managing raw material inventory at Sweet Donuts in Depok City. Sanskara Management and Business, 2(3), 133–145. https://doi.org/10.58812/smb.v2i03.408
Lubis, A. K. (2021). Evaluation of construction waste on projects in Pekanbaru.
Luh, N., Indrayani, A., Hasiholan, B., & Abduh, M. (2021). Implementasi Last Planner System Di Indonesia ( Studi Kasus : 2 Perusahaan Bumn Konstruksi ). Konferensi Nasional Teknik Sipil 15, 2009, 20–21.
Marhani, M. A., Bari, N. A. A., Ahmad, K., & Jaapar, A. (2018). The implementation of lean construction tools: Findings from a qualitative study. Chemical Engineering Transactions, 63, 295–300. https://doi.org/10.3303/CET1863050
Michał, T., & Piotr, J. (2020). Accelerating the Execution of Construction Projects by Relocating Resources. 14–19. https://doi.org/10.3311/ccc2020-041
Mishra, A. K., & Aithal, P. S. (2022). Assessing the Magnitude of Waste Material Using Lean Construction. International Journal of Case Studies in Business, IT, and Education, 6(1), 578–589. https://doi.org/10.47992/ijcsbe.2581.6942.0180
Nikakhtar, A., Hosseini, A. A., Wong, K. Y., & Zavichi, A. (2015). Application of lean construction principles to reduce construction process waste using computer simulation: a case study. International Journal of Services and Operations Management, 20(4), 461–480. https://doi.org/10.1504/IJSOM.2015.068528
Pamungkas, T., Rifai, M., & Soeryodarundino, K. (2024). Penerapan Lean Construction menggunakan Root Cause Analysis dan Metode Borda dalam mengidentifikasi Waste Non-Value Added Activity (Studi Kasus: Proyek Pembangunan Bendungan Jragung Paket I PT Waskita Karya). 1, 14. https://doi.org/10.47134/scbmej.v1i2.2981
Pedrosa, M., Arantes, A., & Cruz, C. O. (2023). Barriers to Adopting Lean Methodology in the Portuguese Construction Industry. Buildings, 13(8), 1–21. https://doi.org/10.3390/buildings13082047
Prieto, A. J., & Alarcón, L. F. (2023). Using Fuzzy Inference Systems for Lean Management Strategies in Construction Project Delivery. Journal of Construction Engineering and Management, 149(9), 4023083. https://doi.org/10.1061/JCEMD4.COENG-12922
Rahayu, R., Sihombing, V., & Irmayani, D. (2024). Pengembangan Sistem Informasi Manajemen Proyek Berbasis Website untuk Optimalisasi Kinerja Tim. Jurnal Sistem Informasi, Teknik Komputer, Dan Teknologi Pendidikan, 4(1), 23–27.
Rumane, A. R. (2017). Quality Management in Construction Projects. CRC Press. https://doi.org/https://doi.org/10.4324/9781315098425
Salam, I. Z., Setiono, S., & Rifai, M. (2023). Implementasi Last Planner System Pada Proyek Pgt. Matriks Teknik Sipil, 11(2), 152. https://doi.org/10.20961/mateksi.v11i2.75614
Singh, S., & Kumar, K. (2021). A study of lean construction and visual management tools through cluster analysis. Ain Shams Engineering Journal, 12(1), 1153–1162. https://doi.org/10.1016/j.asej.2020.04.019
Situmorang, T., Permatasari, A., Johan, R., Laily, N., Farahdiba, I., & Umami, N. (2023). Validitas dan Reliabilitas Instrumen Penilaian Afektif Mata Kuliah Komunikasi dalam Praktik Kebidanan. JURNAL MIDWIFERY Vol 5 No 1, 5(1), 11–20. https://doi.org/10.24252/jmw.v5i1.35189
Sugianto, W., & Putra, B. M. (2022). Penerapan 5S Pada Lembaga Pelayanan Publik untuk Meningkatkan Kualitas Pelayanan. Prosiding Seminar Nasional Ilmu Sosial & Teknologi (Saintek), 4, 284–289.
Sui, P. L., & Joo, C. C. (2001). Just-in-Time Management of Precast Concrete Components. Journal of Construction Engineering and Management, 127(6), 494–501. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:6(494)
Thoengsal, J. (2023). Konstruksi Ramping (lean construction) pada Proyek Konstruksi (Issue November). Insight Mediatama.
Unnikrishnan, S., & Sudhakumar, J. (2024). Identification of wastes and its causes in Indian construction industry based on lean construction practices. International Journal of Construction Management, 0(0), 1–10. https://doi.org/10.1080/15623599.2024.2340376
Wibowo, R. (2023). Implementasi Last Planner System Pada Proyek Tol Kayu Agung – Palembang – Betung Paket Ii Seksi 3. Jurnal Profesi Insinyur Universitas Lampung, 4(1), 25–29. https://doi.org/10.23960/jpi.v4n1.95
Yuniar, R., Handayani, E., & Amalia, K. R. (2023). Analisa Waste Material Konstruksi Dengan Menggunakan Metode Lean Construction Studi Kasus : Pekerjaan Pembangunan Puskesmas Purwodadi Kabupaten Tanjung Jabung Barat. Jurnal Civronlit Unbari, 8(2), 83. https://doi.org/10.33087/civronlit.v8i2.119
Zalfi, A., Movafegh, S. Y., & Tajfar, S. M. A. (2013). Assessment of Jalan Sri Pulai/Lebuhraya Skudai-Pontian signalized intersection performance. Life Science Journal, 10(10). https://doi.org/10.31940/jasl.v6i1.342
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Copyright (c) Salman, Darmawan Pontan, Endah Kurniyaningrum, Tulus Widiarso

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors retain copyright and grant the journal right of first publication and this work is licensed under a Creative Commons Attribution-ShareAlike 4.0 that allows others to share the work with an acknowledgement of the works authorship and initial publication in this journal.
All articles in this journal may be disseminated by listing valid sources and the title of the article should not be omitted. The content of the article is liable to the author.
Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.
In the dissemination of articles by the author must declare the Teras Jurnal as the first party to publish the article.







