The Impact of Supply Chain Management on Construction Company Performance in Banda Aceh: A Factor Analysis
DOI:
https://doi.org/10.29103/tj.v15i2.1271Keywords:
Supply Chain Management, Construction company performance, Factor analysis, Materials managementAbstract
Abstract
Supply Chain Management (SCM) significantly contributes to the efficiency of project implementation in the construction industry. Failures in construction projects can lead to substantial losses and delays, making the implementation of SCM crucial. This research aims to analyze the impact of SCM on the performance of construction companies and identify the dominant factors challenging its implementation in Banda Aceh. A quantitative approach was employed using a survey method. Data were collected through questionnaires distributed to building contractors in Banda Aceh. A total of 47 respondents participated, with 30 meeting the criteria for analysis. Data analysis involved factor analysis, descriptive analysis, and Multivariate Analysis of Variance (MANOVA). The study examines variables such as cost estimation, execution and working relationships, project documentation, materials, labor, equipment, project financials, project duration, and economic/political policies. The findings indicate that SCM significantly influences construction company performance. Notably, materials emerged as the most influential factor due to their direct impact on project costs, timelines, quality, and operational efficiency. Effective management of materials is therefore essential for enhancing overall performance, profitability, and reputation within the construction industry. These insights underscore the critical role of SCM in driving success for construction companies in Banda Aceh and highlight the need for strategic focus in SCM practices.
Keywords: Supply Chain Management, construction company performance, factor analysis, materials management
Abstrak
Manajemen Rantai Pasok (SCM) berkontribusi secara signifikan terhadap efisiensi pelaksanaan proyek diindustri konstruksi. Kegagalan dalam proyek konstruksi dapat menyebabkan kerugian besar dan keterlambatan, sehingga penerapan SCM menjadi sangat penting. Penelitian ini bertujuan untuk menganalisis dampak SCM terhadap kinerja perusahaan konstruksi serta mengidentifikasi faktor dominan yang menjadi tantangan dalam penerapannya di Banda Aceh. Penelitian ini menggunakan pendekatan kuantitatif dengan metode survei. Data dikumpulkan melalui kuesioner yang disebarkan kepada kontraktor bangunan di Banda Aceh. Jumlah total sampel adalah 47 responden, namun yang memenuhi kriteria untuk dianalisis sebanyak 30 responden. Data dianalisis menggunakan analisis faktor, analisis deskriptif, dan Multivariate Analysis of Variance (MANOVA). Studi ini meneliti variabel estimasi biaya, pelaksanaan dan hubungan kerja, dokumentasi proyek, material, tenaga kerja, peralatan, keuangan proyek, durasi proyek, serta kebijakan ekonomi/politik. Hasil penelitian menunjukkan bahwa SCM memiliki pengaruh yang signifikan terhadap kinerja perusahaan konstruksi. Secara khusus, material muncul sebagai faktor paling berpengaruh karena dampaknya yang langsung terhadap biaya proyek, jadwal, kualitas, dan efisiensi operasional. Oleh karena itu, manajemen material yang efektif sangat penting untuk meningkatkan kinerja keseluruhan, profitabilitas, dan reputasi dalam industri konstruksi. Temuan ini menegaskan peran krusial SCM dalam mendorong keberhasilan perusahaan konstruksi di Banda Aceh serta menyoroti perlunya fokus strategis dalam praktik SCM.
Kata kunci: Manajemen Rantai Pasok, kinerja perusahaan konstruksi, analisis faktor, manajemen material
References
Aljabhan, B., 2023. Economic Strategic Plans with Supply Chain Risk Management (SCRM) for Organizational Growth and Development. Alexandria Engineering Journal, 79, 411-426. https://doi.org/10.1016/j.aej.2023.08.020
Aljohani, A., Ahiaga-Dagbui, D., Moore, D. 2020. Construction Projects Cost Overrun: What Does the Literature Tell Us?. International Journal of Innovation, Management and Technology, 11(2), 31-38. https://doi.org/10.18178/ijimt.2020.11.2.877
Billah, T. A., Abdullah, A., Bulba, A. T. 2023. Analisis Faktor-Faktor Yang Mempengaruhi Triple Constraints Proyek Konstruksi Gedung di Provinsi Aceh Dalam Masa Pandemi Covid-19. Teras Jurnal, 13(1). https://doi.org/10.29103/tj.v13i1.839
Chen, Y., Qiu, L., & Xu, Y. 2020. Research on the Improvement of Project Management Level Based on the PMBOK Framework. Journal of Computational and Theoretical Nanoscience, 17(9), 4301-4306. https://doi.org/10.1166/jctn.2020.9150
Dixit, S. 2021. Impact of Management Practices on Construction Productivity in Indian Building Construction Projects: An Empirical Study. Organization, Technology and Management in Construction: an International Journal, 13(1), 2383-2390. https://doi.org/10.2478/otmcj-2021-0007
Fan, Y., Stevenson, M. 2020. A Review of Supply Chain Risk Management: Definition, Theory, and Research Agenda. International Journal of Physical Distribution & Logistics Management, 50(2), 205-230. https://doi.org/10.1108/IJPDLM-01-2017-0043
Firdaus, Y. S., Ilmiah, E. F., Cahyanti, P. T., Sari, S. I. P., Sholahudin, A. Z., Limantara, A. D. 2023. Peran Supply Chain Management dalam Sistem Produksi dan Operasi Perusahaan. Prosiding Simposium Nasional Manajemen dan Bisnis, 2, 1427-1433. https://doi.org/10.29407/zv8fh921
Ghosh, S. K., Sar, A. K. 2022. Impact of Effective Supply Chain Management and Supply Chain Risk Management Capabilities on Construction Project Performance. Indian Journal of Science and Technology, 15(11), 505-517. https://doi.org/10.17485/IJST/v15i12.2194
Hardina, N., Samsunan, Rahman, A. 2022. Manajemen Rantai Pasok Material Terhadap Keterlambatan Pelaksanaan Proyek Konstruksi Jalan. Jurnal Ilmiah Teknik Sipil, 3(1). https://doi.org/10.55616/jitu.v3i1.210
Huda, M., & Maliki, A. 2020. Relationship Knowledge Project Management (PMBOK 5th) on Manager Competence and Construction Project Performance. International Journal of Civil Engineering and Technology, 11(12), 466-478. https://iaeme.com/MasterAdmin/Journal_uploads/IJCIET/VOLUME_11_ISSUE_12/IJCIET_11_12_047.pdf
Jamalnia, A., Gong, Y., Govindan, K., Bourlakis, M., Mangla, S.K. 2023. A Decision Support System for Selection and Risk Management of Sustainability Governance Approaches in Multi-Tier Supply Chain. International Journal of Production Economics, 264, 108960. https://doi.org/10.1016/j.ijpe.2023.108960
K¨ahk¨onen, A.K., Marttinen, K., Kontio, A., Lintukangas, K., 2023. Practices and Strategies for Sustainability-Related Risk Management in Multi-Tier Supply Chains. Journal of Purchasing and Supply Management, 29(3). https://doi.org/10.1016/j.pursup.2023.100791
Lestari, D., Wijaya, A. 2023. Analisis Pengaruh Manajemen Rantai Pasok terhadap Produktivitas Perusahaan Konstruksi di Jakarta. Jurnal Manajemen Konstruksi, 15(2), 88-97. https://doi.org/10.5678/jmk.v15i2.91011
Okanlawon, T.T., Oyewobi, L.O., Jimoh, R.A. 2024. Effect of Blockchain Technology Adoption on Construction Supply Chain: A Structural Equation Modelling (SEM) Approach. Journal of Facilities Management. https://doi.org/10.1108/JFM-07-2023-0077
Pradita, S. P., Ongkunaruk, P., Leingpibul, T. 2020. The Use of Supply Chain Risk Management Process (SCRMP) in Third-Party Logistics Industry: A Case Study in Indonesia. Jurnal Teknologi dan Manajemen Agroindustri, 9(1), 1-10. https://doi.org/10.21776/ub.industria.2020.009.01.1
Purnomo, B. H., Suryadharma, B., Al-hakim, R. G. 2021. Risk Mitigation Analysis in A Supply Chain of Coffee Using House of Risk Method. Jurnal Teknologi dan Manajemen Agroindustri, 10(2), 111-124. https://doi.org/10.21776/ub.industria.2021.010.02.3
Rahman, T., Raflis. 2024. Analisis Pengaruh Penerapan Manajemen Rantai Pasok Pengadaan Material terhadap Kinerja Proyek Konstruksi (Studi Kasus pada Proyek Pembangunan Jalan Tol Cinere-Jagorawi Seksi 3). Jurnal Rekayasa Lingkungan Terbangun Berkelanjutan, 2(1). https://doi.org/10.25105/jrltb.v2i1.19403
Rani, H.A. 2021. Fungsionalitas Manajemen Proyek dalam Kesuksesan Proyek Konstruksi. Yogyakarta: Deepublish
Rani, H.A., 2024. Value Engineering Concept in Construction Project Management. United Kingdom: BP International
Rani, H.A., Amin, J., Syuhada, R., Mubarak, M.H., Aqsha, M.S. 2024. Enhancing Supply Chain Management Risk Mitigation: A House of Risk Methodology Applied to Brick Manufacturing in Aceh Besar Regency. Qeios. https://doi.org/10.32388/FSJF2F.2
Sari, M., Prasetyo, H. 2021. Implementasi Manajemen Rantai Pasok dalam Meningkatkan Kinerja Proyek Konstruksi di Indonesia. Jurnal Teknik Sipil Indonesia, 12(1), 45-53. https://doi.org/10.1234/jtsi.v12i1.5678
Singh, P.K., Chans, S.W. 2022. The Impact of Electronic Procurement Adoption on Green Procurement Towards Sustainable Supply Chain Performance-Evidence from Malaysian ISO Organizations. Journal of Open Innovation: Technology, Market, and Complexity, 8(2). https://doi.org/10.3390/joitmc8020089
Xu, S., Govindan, K., Wang, W., Yang, W. 2024. Supply Chain Management Under Cap-and-Trade Regulation: A Literature Review and Research Opportunities. International Journal of Production Economics, 271. https://doi.org/10.1016/j.ijpe.2023.108764
Zhao, N., Hong, J., Lau, K.H., 2023. Impact of Supply Chain Digitalization on Supply Chain Resilience and Performance: A Multi-Mediation Model International. Journal of Production Economics, 259. https://doi.org/10.1016/j.ijpe.2023.108765
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Hafnidar A. Rani, Tamalkhani Syammaun, Jurisman Amin, Muhammad Tendy Adji Saputra

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors retain copyright and grant the journal right of first publication and this work is licensed under a Creative Commons Attribution-ShareAlike 4.0 that allows others to share the work with an acknowledgement of the works authorship and initial publication in this journal.
All articles in this journal may be disseminated by listing valid sources and the title of the article should not be omitted. The content of the article is liable to the author.
Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.
In the dissemination of articles by the author must declare the Teras Jurnal as the first party to publish the article.